Below is the tentative construction schedule for the entire project. The start and finish dates may change due to weather or unforeseen issues. 



Block 2- Sunset to Brevard Ave
START: May 5, 2016
FINISH: August 15, 2016
Block 3- Brevard Ave- Orlando Ave
START:   June 22, 2016
FINISH:  October 3, 2016
Block 4 - Orlando Ave- Atlantic Ave
START:    October 4, 2016
FINISH:   January 17, 2017
Block 5- Atlantic Ave- Project end
START:    January 18, 2017
FINISH:   April 12, 2017
Traffic Signalization
START:    May 13, 2016
FINISH:   January 11, 2017
Irrigation-Landscape-Hardscape
START:    October 17, 2016
FINISH:   November 21, 2016
Final Paving
START:    January 13, 2017
FINISH:   February 27, 2017